Deed Cards

Deeds.png

Road Closure Required - Add 12 weeks to your build programme

Deeds.png

Next to a school - Council won’t let you start until the school holidays

Deeds.png

Contaminated Land -You must use barrier pipe

Deeds.png

New Site Entrance - Diversionary work required

Deeds.png

December -
Council embargo

Deeds.png

Existing Utility Supplies - Removal

Deeds.png

Tree Protection Order - Can’t dig there

Deeds.png

Easements & Wayleaves - Add 12 weeks to your build programme

Deeds.png

Substation Procurement - 12-16 weeks

Deeds.png

Planning Permission - Do things properly

Deeds.png

Drainage - Preparation & Understanding

Deeds.png

Landlocked - What are your options?